On the basis of Tutorial 05, a sensitivity analysis using the Parameter study module examines how changes in the electricity Working price and Grid usage charge affect the Dynamic payback period and Net present value of the investments.
The article Sensitivity Analysis describes, step by step, how to conduct a parameter study using Tutorial 70.
Reference Case
A simple energy system with two boilers (100 kW and 50 kW) represents the Reference Case.
Variant CHP
In the CHP variant, the smaller boiler from the reference case is replaced by a CHP unit with a Nominal thermal capacity of 60 kW.
Variant CHP and Storage
In the CHP & Storage variant, the system from the CHP variant is supplemented by a storage unit with a capacity of 500 kWh.
Variable Parameters
The Working Price of the Reference Case is the Parameter to be varied.
The Working Prices of the variants are the Additional coupled parameters.